Pressebilder/Press photos

Pressebildene kan lastes ned i høyoppløst versjon ved å klikke på bildet. Bildene kan benyttes fritt under forutsetning av at bildekreditering gjøres. ENGLISH: Illustrations for press in high resolution can be downloaded by clicking the wanted picture underneath. Please use the image crediting stated.

Prosjektdirektør / Project Director

Mr. Erik Smith


Photo: Norwegian National Rail Administration.

Main signalling contract

 

The contract was signed by Tom Tuhus, CEO of Thales Norway (to the left), and Erik Smith, Project Director of the Follo Line Project.

Photo: Håkon Mosvold Larsen, NTB

EPC Civil Oslo S - Illustration

Illustration of the area between Oslo Central Station and the Ekeberg Hill.  

Constructions to be buildt close to Oslo Central Station.

Kontraktssignering / Contract signing

Fra venstre / From the left: 
Ass. jernbanedirektør / Deputy Director General of Norwegian National Rail Administration (NNRA) Mr. Gunnar Løvås, styreleder / Chairman of the Management Board of Condotte Mr. Duccio Astaldi and Project Director of the Follo Line Project, NNRA, Mr. Erik Smith.

Photo: Terje Bendiksby (NTB)

JBT Rive reetablere

Signering for kontrakten JBT Rive Reetablere ved delprosjekt Innføring Oslo S. Kontrakten ble signert av fra venstre: Thor Svegården, styreleder i Baneservice og Erik Smith, prosjektdirektør i Follobaneprosjektet.

EPC Ski

Ankara-Istanbul High-Speed Line. Turkey

 

Airport Link Miami, Florida, USA

Photos: Obrascón Huarte Lain S.A.

EPC Ski

Kontraktssignering / Contract signing

Fra venstre /From the left:

Europe Area Director Mr. José Emilio Pont Pérez of Obrascón Huarte Lain S.A., Ass. jernbanedirektør / Deputy Director General Mr. Gunnar Løvås of NNRA and Prosjektdirektør Follobaneprosjektet / Project Director of the Follo Line Project Mr. Erik Smith of Norwegian National Rail Administration (NNRA).

Photo: Jon Olav Nesvold, NTB.

EPC TBM

Kontraktssignering / Contract signing

Fra venstre / From the left:

Project Director of the Follo Line Project, Norwegian National Rail Administration (NNRA), Mr. Erik Smith, Ass. jernbanedirektør / Deputy Director General of NNRA Mr. Gunnar Løvås, Project Director Fernando Vara Ortiz of Acciona and Ing. Massimo Maffucci of Ghella.


Photo: Cornelius Poppe, NTB.

 EPC Drill & Blast

Kontraktssignering / Contract signing

Fra venstre / From the left: 
Ass. jernbanedirektør / Deputy Director General of Norwegian National Rail Administration (NNRA) Mr. Gunnar Løvås, styreleder / Chairman of the Management Board of Condotte Mr. Duccio Astaldi and Project Director of the Follo Line Project, NNRA, Mr. Erik Smith.


Photo: Heiko Junge, NTB.

Oslo S / Oslo Central Station

Follobanen - oversiktsbilde fra Oslo S mot Ekebergåsen.

The Follo Line - view from Oslo Central Station towards the Ekeberg hill.

Illustration: Norwegian National Rail Administration/ViaNova.

Kontrakt signert for arbeider ved Oslo S

 

Kontraktssignering

Til venstre Anders Geirsta, regiondirektør i Skanska Norge AS og til høyre Erik Smith, prosjektdirektør i Follobaneprosjektet 


Foto: Gunnar Børseth, Jernbaneverket.

 

Åsland riggområde

Åsland riggområde, sør i Oslo: Her skal to tunnelboremaskiner (TBM) bore seg mot Oslo S og to TBM'er mot Ski.

Illustrasjon: Jernbaneverket/ViaNova.

TBM construction site Åsland

The Follo Line Project has one major constrution site at Åsland. From the rig area two TMBs will be working towards Oslo Central Station, and two TBMs will be working towards Ski.

Illustration: Norwegian National Rail Administration/ViaNova.

EPC Ski

Ny undergang under jernbanen ved Roås nord for Ski.
A new culvert under the Østfold Line at Roås, north of Ski city centre.

Photo: The Follo Line Project, Norwegian National Rail Administration

EPC Ski

Langhusveien ferdig omlagt nord for Ski.
The new and relocated Langhus road, north of Ski city centre.

Photo: B. RønningThe Follo Line Project, Norwegian National Rail Administration

Åsland riggområde / Åsland rig area

Tunneldriving i den ene atkomsttunnelen på Åsland.

Excavation by Drill & Blast at Åsland.


Photo: The Follo Line Project, Norwegian National Rail Administration.

Åsland riggområde / Åsland rig area

De to atkomsttunnelene som går inn fra Åsland vil brukes til inn- og utgående trafikk til hovedtunnelen, og steinmassene skal fraktes ut på transportbånd.

The two access tunnels will cater for traffic to and from the main tunnel Åsland, as weill as removal of excavated materials by belt conveyors to the rig area.


Photo: The Follo Line Project, Norwegian National Rail Administration.

Nye Ski stasjon / New Ski station

Nye Ski stasjon sett fra luften.

The new Ski Station seen from the air. The new Ski Station will be built with sex tracks and three central platforms, a new pedestrian underpass, a new road bridge, bus terminal and enlarged car park.


Illustration: Norwegian National Rail Administration/Multiconsult.

Nye Ski stasjon / New Ski station

Trappeamfi øst for nye Ski stasjon.

The area east of the new Ski Station. Accessibility, efficient transport and integration, into the urban landscape are important factors to the Norwegian National Rail Administration.

Illustration: Norwegian National Rail Administration/Multiconsult.

Tidslinje for Follobaneprosjektet

Tidslinjen viser de viktigste milepælene for Follobaneprosjektet fra 2012 til ferdigstillelsen planlagt i desember 2021.

Illustrasjon: Follobaneprosjektet, Jernbaneverket.


Timeline for the Follo Line Project

The timeline for the Follo Line Project shows the milestones from 2012 and to the completed Follo Line planned in December 2021.

Illustration: Norwegian National Rail Administration.

Hovedtunnelen / The main tunnel

Nordens hittil lengste jernbanetunnel, og den første i Norge med med to atskilte løp.

The longest railway tunnel in the Nordic countries, and Norway's first long twin tube rail tunnel.


Illustration: Norwegian National Rail Administration.

Drill & Blast

Tunneldriving med sprengning.

Tunnel excavation by Drill & Blast.


Photo: Hilde Lillejord, Norwegian National Rail Administration.